Our Bathroom Process
At Affordable Bathrooms, you can choose one of our packages and let us supply all materials and labor, or you can choose to let us install your own materials. Whatever you choose, we will give you a beautiful bathroom in 7 days or less.
Take a look at one of our remodeling projects, and see the entire process from start to finish:
DAY 1
We removed the tub and tub surround. We removed the shower fixtures and shower body, toilet, vanity and mirror. We removed all tile floors, cleaned up and put all debris in a dumpster bag.
DAY 2
Installed new shower body, shower valve, and drain. Install new 1/2 inch cement board and set new metal tub.
DAY 3
Applied a light coat of joint compound over any holes and drywall damage throughout. Laid tile floors and let set for 24 hours.
DAY 4 & 5
Installed tile for tub surround. Grout all tile for shower walls and floors. Cleaned excess grout off tile walls and floor.
DAY 6
Installed vanity, counter-tops and sink, set sink and shower faucets and connect all water lines. Set toilet and connect water line. Hung mirror and replaced light fixture.
DAY 7
Paint walls, and installed towel rod, toilet paper holder, switch plate and outlet cover. Clean up and dispose of any final debris before we schedule for the dumpster bag pickup.